TVA inspector general finds 4-year parts audit lapse at Watts Bar Nuclear Plant

Posted: Updated:

KNOXVILLE, Tenn. — A report by the Tennessee Valley Authority's inspector general says the federal utility missed quality assurance audits at the Watts Bar Nuclear Plant.

According to the Knoxville News Sentinel the Office of Inspector General said no audits were done on commercial-grade materials being used to build Unit 2 at the power plant in Spring City for four years. The report also noted TVA has taken steps to prevent a repeat of the lapse and has hired independent evaluators to review the materials in question.

The Nuclear Regulatory Commission cited TVA for the breakdown in auditing that allowed thousands of parts bought for the reactor project to bypass being documented as nuclear grade.

Copyright 2013 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Powered by WorldNow
Can't find what you're looking for?

WRCB-TV
900 Whitehall Road
Chattanooga, TN 37405
(423) 267-5412

WRCB Jobs EEO | FCC Public Files

Powered by WorldNow
All content © Copyright 2000 - 2014 WorldNow and WRCB. All Rights Reserved. For more information on this site, please read our Privacy Policy and Terms of Service.