Camp Jordan to undergo improvements

Posted: Updated:

EAST RIDGE, TN. (WRCB) -- As part of its commitment to continually improve its facilities, the City of East Ridge announced today the Greenway path at Camp Jordan will be paved from Aug. 4-9. Portions of the path will be available for the public to use throughout the process. 

Schedule of Closed Portions:

August 4 -- West area (left of the Arena) closed for base layer

August 5 -- East area (Arena side) closed for base layer

August 6 -- West area (left of the Arena) closed for pavement layer

August 7 or 9 -- East area (Arena side) closed for pavement layer

Visitors are asked to heed all informational signs and avoid portions of the path that are under construction. The greenway paving is a stimulus funded project. For questions or further information contact Camp Jordan offices at 423-490-0078 or visit www.eastridgetn.org.